North Renfrew Times
June 22, 2011

NRU back online

NRU is back up and running, ahead of schedule and no worse for wear.

Atomic Energy of Canada Ltd announced last week that the National Research Universal (NRU) reactor at Chalk River had returned to operation from its planned extended outage.

AECL said vessel inspection results to date confirmed that there are no detectable changes to the vessel wall, no detectable corrosion, and that the inspected welds, applied during the 2010 repairs “continue to be sound.”

“The NRU is currently operating at high power, producing medical isotopes and providing vital research and testing support to the science community, universities, and industry from across Canada and around the world,” the company said.

The purpose of the 32-day outage was to perform maintenance and inspection work designed to enhance the reliability of NRU and to fulfill AECL’s commitment to the Canadian Nuclear Safety Commission (CNSC).

This was the first annual planned extended outage for NRU following the reactor's 15-month shutdown that ended last August.

That shutdown was required to repair areas of corrosion on the wall of the reactor vessel.

As part of its approval to restart the reactor, the CNSC required that AECL close down the reactor for a month at a time once a year to do maintenance and repairs.

The first outage was to start no later than nine months after NRU restarted last August.

Planning and preparations for the outage began in March 2010 and continued up to the start of the outage on May 15, the company said.

“It was a complex endeavour, consuming over 25,000 hours of planning and execution.

“Contributions were made from over 120 individuals representing AECL’s skilled trades, technicians, engineers, radiation protection specialists, and project staff.”

In addition to AECL staff, 50 contract employees representing seven Canadian companies also contributed to the completion of the project, the company said.

During the outage, AECL completed over 1,400 work activities, including preventative maintenance, inspections, and condition assessments as well as equipment repairs, upgrades, and replacements in priority areas critical to the safe and reliable operation of the NRU.

Inspection activities examined the five highest priority vessel sites, including three sites that were inaccessible prior to the development and use of first of a kind inspection tooling, the company said.

“While improving accessibility, the tooling also allowed the vessel to remain fuelled and filled with heavy water during inspections.

“Challenges experienced in the use of this new equipment provided AECL staff and contractors insights into equipment limitations and learning opportunities for use in future outages.”

Inspections and other activities not completed during this outage, such as lower level preventative maintenance, have been deferred to future scheduled short duration outages, AECL added.

In a video posted to the website nrucanada.ca, Ted Moryto, one of the team leaders of the NRU Planned Extended Outage Project, said inspection results showed to a “micron level” that there has been no corrosion of the repairs to the reactor vessel.

The results were “as good as we could have expected,” he said.

“We have demonstrated and observed that the mitigation measures we have undertaken over the past 18 months to address these concerns have been very effective,” he said.

New data gained during subsequent inspections will be analyzed and the results will be included in the NRU “Fitness for Service” report.

The completed report will be issued to the CNSC by September 2011.


>> Back to homepage