North Renfrew Times
July 27, 2011

Town faces costly arena upgrades

by Vance Gutzman

A recommendation to spend more than $300,000 on capital upgrades to the Deep River Arena has been put on ice, for the time being, by town council.

Council tabled a resolution last week which, had it been approved, would have initiated the tendering process to address fire safety deficiencies at the arena.

Those deficiencies were identified following the release, this past February, of a review of the town's fire protection services by the Ontario Fire Marshal's office (OFM).

That lengthy review, which was initiated by the OFM as a result of concerns stemming from its investigation into a fatal fire last fall, contained 11 recommendations - one of which was for the Deep River Fire Service to initiate an inspection program of all higher risk occupancies in the municipality.

 In making that recommendation, the OFM noted that a spot audit it conducted with the fire department of four such buildings, including the arena, found they were not in compliance with the Ontario Fire Code.

The town and its fire service acted quickly upon that, and other recommendations contained in the OFM's review, and all 17 such "high risk" occupancies had been thoroughly inspected less than two months after the review was issued.

The town also hired a building and inspections consultant to inspect the town's own high-occupancy buildings, including the arena.

Subsequent to that, the deficiencies identified in the consultant's report were reviewed by two contractors, who then provided the municipality with a list of the work required to address them.

The contractors, whose names are not mentioned in an issue report issued by the town's chief building official, Robert Labre, also provided cost estimates for the work.

The list of the work contained in Labre's issue report is expansive and the cost estimates are expensive.

Retrofit upgrades alone are estimated at $160,000, and would include such things as installing new laminate fire-rated drywall over the existing wood-panelling in the lower viewing area.

The second major bit of work  that needs to be done, according to Labre's report, involves installing a sprinkler system in the building - a dry sprinkler system for the unheated area and wet system to protect the heated areas.

In a wet sprinkler system, a network of pipes is filled with water. When the system goes off, water is released from several sprinklers in an effort to douse any nearby flames. In a dry sprinkler system, the pipes are filled with air instead of water. When the system goes off, water quickly pours first into the pipes, and then out of the sprinklers.

The cost of installing the two types of sprinkler systems is estimated at $145,000.

"This building was built in the 1970s," Labre told town council last week.

"It's a wooden structure and a high-risk fire hazard."

Labre also gave council two options - perform the necessary upgrades, or take no action whatsoever.

And while the cost estimates gave some council members a case of sticker shock, the timelines for completing the work were also on their minds.

"Can we not open the arena in September," Councillor Terry Myers asked Labre, who, in turn, was able to throw a little sun at the rain.

While the total scope of the work might take two months to complete, Labre said the Fire Marshal's office might cut the town some slack if it sees the work has at least been started.

"If they see you are improving safety, they will definitely give you more time," Labre said.

And the town is fortunate, Labre added, in that the water main at the arena is capable of accepting a sprinkler system with the costly addition of a booster pump.

"At $305,000 I don't feel so fortunate," Mayor David Thompson said with a glum look on his face.

Although the resolution was tabled last week, the recommendations outlined in Labre's report will be discussed in greater detail between the chief building official and new fire chief Gene Thompson, as well as a representative from the OFM.


>> Back to homepage